SCHOOL CAMPUS

SIA has been looking for a permanent location since its founding in the fall of 2015. In the spring of 2019, the facility at 777 E Magnesium Rd was identified and chosen by the board as the most viable option for SIA's future. The property consists of a 3-story office building built in 1988 situated on roughly 7 acres. 

Building Details:

Total Enrollment - 980 (when fully enrolled K-12)

Total Space - 101,370 sq. ft.

Phase 1 Development (February 2020 - September 2020)

Project Management - Washington State Charter School Development (WCSD)

Architect - D3 Architects

General Contractor - TW Clark

Scope of Project - Renovation of 2nd floor into classrooms, 1st floor cafeteria and site work (new entrance, bus loop and parking lot)

Phase 2 Development (February 2021 - December 2021)

Project Management - NAC Architecture

Architect - NAC Architecture

General Contractor - TW Clark

Scope of Project - Renovation of remaining spaces inside building on the 1st and 3rd floor including the addition of middle and high school classrooms on the 3rd floor, art spaces, school library, science lab for secondary students, dedicated fitness areas, specialist classrooms, and playground.

Substantial Completion - December 2021